Back to flash example project  
   

Step 1

The site of the proposed conservatory

 

Step 2

Construction work begins. The ground is excavated to a minimum of 450mm deep for the footings. Excavation exposes on underground drainage pipe.
     

Step 3

Additional steel mesh reinforcement is introduced to the concrete foundation to prevent the drainage pipe being crushed.

Step 4

Concrete is poured into the trench to form the foundations. The concrete is a minimum of 150mm thick.
       
 

Step 5

The concrete is floated to form a level surface to build upon.

Step 6

The inner leaf of the cavity wall is built up to floor level.
       
 

 

Step 8

A blinding screed of sand is laid over the hardcore to prevent any sharp stones puncturing the damp proof membrane.

Step 7

Hardcore is laid to a minimum 100mm deep and compacted to form the base layer of the slab
 
 

 

Step 9

A visqueen damp proof membrane is laid over the sand blinding and lapped onto the inner leaf of brickwork.
 

Step 10

Optional floor insulation may be installed at this stage.
 
 

Step 11

Concrete 100mm thick is laid to bring the slab up to the finished floor level
 

Step 12

The concrete is floated to a smooth level surface, suitable of tiling or carpet.
 
 

Step 13

The outer leaf of the wall is built. In this case, artificial stone to match the house is used.
 

Step 14

The inner leaf of the cavity wall is built to complete the basework. The same material as the outer leaf has been used to provide a feature stone finish.
 

Step 15

On this installation cavity trays are being installed due to the porosity of the house wall and the exposed conditions which the conservatory faces.


Step 16

A close up of a cavity tray.
 
 

Step 17

The final cavity tray is installed.
 

Step 18

The house wall is pointed after the installation of the cavity trays and lead flashings.
 

Step 19

The PVCu external cill is fitted to the dwarf wall and erection of the side frames begins.

Step 20

On completion of the frames the structural aluminium eaves beam is fitted to the head of the frames.
 
 

Step 21

The PVCu thermally clad aluminium glazing bars and ridge system are quickly assembled.
 

Step 22

The polycarbonate glazing panels are installed (alternatively, double glazed units may be specified)
 
 

Step 23

The ventilated aluminium ridge is ready to accept the clip fit PVCu internal cladding. Electrical cables may be concealed behind the cladding if a fan or lights are required.
 

Step 24

The PVCu internal fascia is clipped onto the eaves beam to complete the internal finishing trims.
 

Step 25

The completed conservatory
   
 
Zeta Commerce Websites